Brief → concept → develop → specify → deliver. Five gates, updated estimate at each.
Lifestyle audit + survey
Layouts + mood
Materials + 3D
FF&E + lighting
Build + styling
| Gate | You receive | Estimate update | Typical duration |
|---|---|---|---|
| 01 Brief | Programme doc, as-built dimensions, inspiration brief | Indicative band (±20%) | 1 week |
| 02 Concept | 2 layout options, material direction, 3D sketch views | Refined band (±15%) | 2–3 weeks |
| 03 Developed | Final layout, elevations, lighting concept, joinery sketches | Line-item draft (±12%) | 4–5 weeks |
| 04 Specification | FF&E schedule, contractor pack, tender drawings | Binding quote (±5%) | 3–4 weeks |
| 05 Delivery | Site supervision log, snag list, styling, photo handover | Final account | Project-dependent |
Two structured revision rounds per gate—changes outside scope quoted separately.
Drawings, schedules, and estimate versions in one shared folder.
Weekly reports on build packages; daily photos during critical install weeks.